PJM-AI1-133
50 MW hybrid in Fleming, KY · In queue since September 2022 · Proposed COD April 2029
50 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-30
PJM-AI1-133 is a proposed 50 MW hybrid solar and battery project located in Fleming County, Kentucky. The project, which consists of 50 MW of solar generation, is being developed within the PJM Interconnection queue. Its queue entry date is September 8, 2022, with a proposed commercial operation date of April 30, 2029. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The interconnecting utility is EKPC, and the point of interconnection (POI) is the Hillsboro 69 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
Fleming
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Hillsboro 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HILLSBRO138 KV HLSBRO
- POI Substation
- Hillsboro Substation