PJM-AI1-134
200 MW hybrid in Grant, IN · In queue since September 2022 · Proposed COD April 2029
200 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Total Duration
6y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-04-30
PJM-AI1-134 is a proposed 200 MW hybrid solar and battery project located in Grant County, Indiana. The project, which interconnects to the AEP utility via the Greentown - Hummel Creek 138 kV point of interconnection, entered the PJM interconnection queue on September 8, 2022, with a proposed commercial operation date of April 30, 2029.
The interconnection agreement is currently listed as "In Progress (unknown study)". The project consists of 200 MW of solar generation capacity, with battery storage also planned as part of the hybrid development.
Generated from interconnection queue and public data sources
State
IN
County
Grant
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Greentown - Hummel Creek 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- HUMMEL 18 KV CTG11
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-134