PJM-AI1-145
125 MW generation in Prince Edward, VA · In queue since September 2022 · Proposed COD September 2026
125 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
4 years
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
PJM-AI1-145 is a proposed solar generation project with a total capacity of 125 MW, located in Prince Edward County, Virginia. The project is being developed within the Dominion service territory and interconnected to the Farmville - Moran DP 115 kV point of interconnection.
The project entered the PJM interconnection queue on September 9, 2022, with a proposed commercial operation date of September 30, 2026. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
VA
County
Prince Edward
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Farmville - Moran DP 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-145