Project PJM-AI1-148 — Project Summary

Queue ID
PJM-AI1-148
Capacity
164 MW
Technology
Solar
Status
active
Location
Kankakee, IL
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AI1-148

PJM-AI1-148BetaActiveSolarPJMLBNL + Live

164 MW generation in Kankakee, IL · In queue since September 2022 · Proposed COD January 2026

164 MW

Capacity

1

Components

Solar

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection

Total Duration

3y 4m

Schedule

4 months past proposed COD

In Study38%
Queue EntrySep 9, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-01-01

About

PJM-AI1-148 is a proposed solar generation project with a total capacity of 164 MW, located in Kankakee County, Illinois. The project is being developed within the PJM Interconnection queue, with an entry date of September 9, 2022, and a proposed commercial operation date of January 1, 2026. The project is interconnected with ComEd at the Davis Creek 138kV point of interconnection.

The interconnection agreement (IA) for PJM-AI1-148 is currently in progress, with the specific study being conducted not specified in available data. The project consists solely of solar photovoltaic generation, with no battery storage or other generation types included in the listed components.

Generated from interconnection queue and public data sources

Project Details

State

IL

County

Kankakee

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

ComEd

Entity

PJM

Service Type

Point of Interconnection

Davis Creek 138kV

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
N ILLINOIS HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
86 DAVIS138 KV TR71
POI Substation
ComEd Davis Creek Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project PJM-AI1-148