PJM-AI1-150
49.9 MW hybrid in Butler, OH · In queue since September 2022 · Proposed COD January 2027
49.9 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-04
PJM-AI1-150 is a proposed 49.9 MW hybrid solar and battery energy storage project located in Butler County, Ohio. The project, which consists of 49.9 MW of solar generation, is in the PJM interconnection queue as of September 9, 2022, with a proposed commercial operation date of January 4, 2027. The point of interconnection is the Locust - Todd 69 kV line.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The utility involved is Dayton. The project is listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
OH
County
Butler
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Locust - Todd 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-150