PJM-AI1-153
20 MW hybrid in Dauphin, PA · In queue since September 2022 · Proposed COD January 2027
20 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-01-04
PJM-AI1-153 is a proposed 20 MW hybrid solar and battery project located in Dauphin County, Pennsylvania. The project consists of 20 MW of solar generation. It is listed in the PJM interconnection queue with an entry date of September 9, 2022, and a proposed commercial operation date of January 4, 2027.
The interconnection status for PJM-AI1-153 is listed as "In Progress (unknown study)". The point of interconnection is the North Hershey - Grantville 69 kV line.
Generated from interconnection queue and public data sources
State
PA
County
Dauphin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ME
Entity
PJM
Service Type
—
Point of Interconnection
North Hershey - Grantville 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-153