PJM-AI1-161
1.4 MW generation in Crawford, PA · In queue since September 2022 · Proposed COD January 2028
1.4 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-01
The proposed project PJM-AI1-161 is a 1.4 MW solar generation project located in Crawford County, Pennsylvania. It is interconnected within the PJM Interconnection queue, having entered the queue on September 9, 2022, with a proposed commercial operation date of January 1, 2028. The project is currently listed as "active" in the queue, with its Interconnection Agreement (IA) status "In Progress (unknown study)".
The project is being developed within the PENELEC utility territory. The point of interconnection (POI) is Crawford Solar 3 34.5 kV. The project has appeared in recent news coverage regarding renewable energy development in the PJM region.
Generated from interconnection queue and public data sources
State
PA
County
Crawford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Crawford Solar 3 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-161