PJM-AI1-167
250 MW storage in Clermont, OH · In queue since September 2022 · Proposed COD December 2028
250 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
6y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
PJM-AI1-167 is a proposed 250 MW battery storage project located in Clermont County, Ohio. The project, which consists entirely of battery technology, is interconnected within the PJM Interconnection queue. Its queue entry date is September 9, 2022, with a proposed commercial operation date of December 31, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is within the service territory of Duke Energy Ohio & Kentucky (DEOK). The point of interconnection is the Cedarville 138 kV substation.
Generated from interconnection queue and public data sources
State
OH
County
Clermont
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DEOK
Entity
PJM
Service Type
—
Point of Interconnection
Cedarville 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-167