PJM-AI1-168
200 MW generation in Coshocton, OH · In queue since September 2022 · Proposed COD August 2027
200 MW
Capacity
1
Components
Wind
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-08-31
PJM-AI1-168 is a proposed 200 MW wind generation project located in Coshocton County, Ohio. The project, which entered the PJM interconnection queue on September 9, 2022, is slated for a proposed commercial operation date of August 31, 2027. The interconnecting utility is AEP, and the point of interconnection is the Conesville 345 kV substation.
The project's interconnection agreement status is listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
OH
County
Coshocton
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Conesville 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CONESVIL4 KV CVD
- POI Substation
- Conesville Station
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.