PJM-AI1-171
100 MW generation in Whiteside, IL · In queue since September 2022 · Proposed COD April 2028
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-30
PJM-AI1-171 is a proposed solar generation project with a total capacity of 100 MW, located in Whiteside County, Illinois. The project is interconnected within the PJM Interconnection queue under queue ID AI1-171, with an entry date of September 10, 2022. The proposed commercial operation date is April 30, 2028. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project, which falls within the ComEd utility territory, consists of 100 MW of solar photovoltaic generation. The point of interconnection is the Garden Plain - Rock Falls 138 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Whiteside
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Garden Plain - Rock Falls 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 133 ROCK34.5 KV STERLBS
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-171