PJM-AI1-172
250 MW hybrid in Grundy, IL · In queue since September 2022 · Proposed COD April 2028
250 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-04-30
PJM-AI1-172 is a proposed 250 MW hybrid solar and battery project located in Grundy County, Illinois. The project consists of 250 MW of solar generation and an unspecified amount of battery storage. It is interconnected within the PJM Interconnection queue as project PJM-AI1-172, with a queue entry date of September 10, 2022.
The proposed commercial operation date for PJM-AI1-172 is April 30, 2028. The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Katydid Road - Goodings Grove 345 kV line, and the interconnecting utility is ComEd.
Generated from interconnection queue and public data sources
State
IL
County
Grundy
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Katydid Road - Goodings Grove 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.