PJM-AI1-173
16 MW generation in Stephenson, IL · In queue since September 2022 · Proposed COD April 2027
16 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-04-30
PJM-AI1-173 is a proposed 16 MW solar generation project located in Stephenson County, Illinois. The project is interconnected within the ComEd service area of the PJM Interconnection queue. The project entered the queue on September 10, 2022, and has a proposed commercial operation date of April 30, 2027. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The proposed project consists of 16 MW of solar photovoltaic generation. The point of interconnection is the Lena - Freeport 34.5 kV line.
Generated from interconnection queue and public data sources
State
IL
County
Stephenson
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Lena - Freeport 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-173