PJM-AI1-180
100 MW hybrid in KY · In queue since September 2022 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-180 is a proposed 100 MW hybrid solar and battery project located in Kentucky within the PJM Interconnection region. The development project, consisting of 100 MW of solar generation, entered the PJM queue on September 9, 2022, with a proposed commercial operation date of December 31, 2027. The interconnecting utility is East Kentucky Power Cooperative (EKPC).
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Windsor 69 kV substation.
Generated from interconnection queue and public data sources
State
KY
County
—
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
EKPC
Entity
PJM
Service Type
—
Point of Interconnection
Windsor 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EWINDSOR
- POI Substation
- East Windsor Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-180