PJM-AI1-181
140 MW storage in Venango, PA · In queue since September 2022 · Proposed COD December 2027
140 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-181 is a proposed 140 MW battery storage project located in Venango County, Pennsylvania. The project, which consists entirely of battery storage, is interconnected within the PJM Interconnection queue. Its queue entry date is September 9, 2022, with a proposed commercial operation date of December 31, 2027. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is located within the PENELEC utility territory and connects to the Grandview 115 kV point of interconnection. The developer is not specified in the available data. The project is listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
PA
County
Venango
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Grandview 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WSIDE 34 KV LASALLE
- POI Substation
- Grandview Ave Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-181