PJM-AI1-183
130 MW storage in Richmond, VA · In queue since September 2022 · Proposed COD December 2027
130 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-183 is a proposed 130 MW battery storage project located in Richmond County, Virginia. The project is being developed within the Dominion service area and is interconnected to the PJM Interconnection queue. The project entered the queue on September 9, 2022, with a proposed commercial operation date of December 31, 2027.
The interconnection agreement (IA) for PJM-AI1-183 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) for the project is the DuPont - Marlboro 115 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Richmond
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
DuPont - Marlboro 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-183