PJM-AI1-184
110 MW storage in Frederick, VA · In queue since September 2022 · Proposed COD December 2027
110 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-184 is a proposed 110 MW battery storage project located in Frederick County, Virginia. The project, which consists entirely of battery storage, is interconnected within the PJM Interconnection queue. Its queue entry date is September 9, 2022, with a proposed commercial operation date of December 31, 2027. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The designated point of interconnection (POI) is the Greenwood 138 kV substation.
The project's listed utility is APS, and it is currently in the active stage of the interconnection queue process. Recent news coverage indicates public interest in the development of battery storage projects within the PJM region.
Generated from interconnection queue and public data sources
State
VA
County
Frederick
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Greenwood 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GREENWOO138 KV GREENWD
- POI Substation
- Greenwood Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-184