PJM-AI1-187
280 MW storage in Hunterdon, NJ · In queue since September 2022 · Proposed COD December 2027
280 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-187 is a proposed 280 MW battery storage project located in Hunterdon County, New Jersey. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 9, 2022. The proposed commercial operation date is December 31, 2027.
The interconnection agreement for the project with utility JCPL is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
NJ
County
Hunterdon
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Glen Gardner 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GLENGARD34 KV LEBANSP
- POI Substation
- Glen Gardner Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.