PJM-AI1-188
130 MW storage in Erie, PA · In queue since September 2022 · Proposed COD December 2027
130 MW
Capacity
1
Components
Battery
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-188 is a proposed 130 MW battery storage project located in Erie County, Pennsylvania. The project, which consists entirely of battery storage, is interconnected within the PJM Interconnection queue. The project entered the queue on September 9, 2022, with a proposed commercial operation date of December 31, 2027. Its interconnection agreement status is currently listed as "In Progress (unknown study)".
The development project is located within the PENELEC utility service area.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Buffalo 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- POI Substation
- Buffalo Tungsten Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.