PJM-AI1-190
100 MW hybrid in Union, OH · In queue since September 2022 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
5y 3m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI1-190 is a proposed 100 MW hybrid solar and battery project located in Union County, Ohio. The project consists of 100 MW of solar generation. It is listed in the PJM interconnection queue as of September 9, 2022, with a proposed commercial operation date of December 31, 2027. The point of interconnection is at the Eagle Road 138 kV substation.
The interconnection agreement for the project with utility Dayton is currently listed as "In Progress (unknown study)". The project is listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Union
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dayton
Entity
PJM
Service Type
—
Point of Interconnection
Eagle Road 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-190