PJM-AI1-192
40 MW generation in Marion, WV · In queue since September 2022 · Proposed COD June 2024
40 MW
Capacity
1
Components
Gas
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
23 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-01
PJM-AI1-192 is a proposed 40 MW gas-fired generation project located in Marion County, West Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on September 9, 2022, with a proposed commercial operation date of June 1, 2024. The interconnecting utility is APS.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Price Hill - Pruntytown 138 kV line.
Generated from interconnection queue and public data sources
State
WV
County
Marion
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Price Hill - Pruntytown 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PRUNTYTOWN
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-192