PJM-AI1-211
68 MW hybrid in Preston, WV · In queue since September 2022 · Proposed COD December 2024
68 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
2y 3m
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
PJM-AI1-211 is a proposed 68 MW hybrid solar and battery project located in Preston County, West Virginia. The project consists of 68 MW of solar generation. It is in the PJM interconnection queue as of September 10, 2022, with a proposed commercial operation date of December 31, 2024. The interconnection agreement (IA) status is listed as "In Progress (unknown study)".
The proposed project is interconnected to the APS utility at the Brandonville - Necessity 138 kV point of interconnection.
Generated from interconnection queue and public data sources
State
WV
County
Preston
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Brandonville - Necessity 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI1-211