PJM-AI1-214
20 MW hybrid in Centre, PA · In queue since September 2022 · Proposed COD June 2024
20 MW
Capacity
1
Components
Solar
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
22 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-06-30
PJM-AI1-214 is a proposed 20 MW hybrid solar and battery project located in Centre County, Pennsylvania. The project consists of 20 MW of solar generation, and is being developed within the PJM Interconnection queue. The project entered the queue on September 10, 2022, with a proposed commercial operation date of June 30, 2024.
The interconnection agreement for PJM-AI1-214 is currently listed as "In Progress (unknown study)". The point of interconnection is the Philipsburg 115 kV IV substation, and the interconnecting utility is PENELEC.
Generated from interconnection queue and public data sources
State
PA
County
Centre
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Philipsburg 115 kV IV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PHILIPSB115 KV UNSH_SP
- POI Substation
- Philipsburg Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.