Project PJM-AI1-215 — Project Summary

Queue ID
PJM-AI1-215
Capacity
20 MW
Technology
Solar+Battery
Status
active
Location
Centre, PA
Region
PJM
Developer
IA Status
In Progress (unknown study)

PJM-AI1-215

PJM-AI1-215BetaActiveSolarBatteryPJMLBNL + Live

20 MW hybrid in Centre, PA · In queue since September 2022 · Proposed COD June 2024

20 MW

Capacity

1

Components

Solar

3y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection

Total Duration

1y 9m

Schedule

22 months past proposed COD

In Study38%
Queue EntrySep 10, 2022

Interconnection request submitted to ISO/RTO

System Impact StudyCurrent

PJM processes interconnection requests through multi-phase System Impact Studies (SIS).

Typical: ~48 months (historically longest)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-06-30

About

PJM-AI1-215 is a proposed 20 MW hybrid solar and battery project located in Centre County, Pennsylvania. The project consists of 20 MW of solar generation. It is interconnected within the PJM Interconnection queue, with an entry date of September 10, 2022. The proposed commercial operation date is June 30, 2024. The interconnection agreement status is listed as "In Progress (unknown study)".

The project is located within the PENELEC utility territory. The point of interconnection is the Philipsburg 115 kV V substation.

Generated from interconnection queue and public data sources

Project Details

State

PA

County

Centre

Grid Region

PJM Interconnection

Market

ISO/RTO Member

Developer

Utility

PENELEC

Entity

PJM

Service Type

Point of Interconnection

Philipsburg 115 kV V

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
PJM
Trading Hub
WESTERN HUB
Hub Confidence
HIGH
Nearest Node (Estimated)
PHILIPSB115 KV UNSH_SP
POI Substation
Philipsburg Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.