PJM-AI2-002
150 MW storage in Washington, VA · In queue since October 2022 · Proposed COD May 2028
150 MW
Capacity
1
Components
Battery
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Total Duration
5y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-05-26
PJM-AI2-002 is a proposed 150 MW battery storage project located in Washington County, Virginia. The project, which consists entirely of battery storage, is being developed within the PJM Interconnection queue. Its queue entry date is October 1, 2022, with a proposed commercial operation date of May 26, 2028. The point of interconnection is at the Vanceville 138 kV substation.
The project's interconnection agreement status is currently listed as "In Progress (unknown study)". The designated utility is APS. The project has appeared in recent news coverage regarding energy storage development in the PJM region.
Generated from interconnection queue and public data sources
State
VA
County
Washington
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
APS
Entity
PJM
Service Type
—
Point of Interconnection
Vanceville 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-002