PJM-AI2-007
40 MW storage in Kane, IL · In queue since November 2022 · Proposed COD June 2027
40 MW
Capacity
1
Components
Battery
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
PJM-AI2-007 is a proposed 40 MW battery storage project located in Kane County, Illinois. The project is interconnected within the ComEd service area and participates in the PJM Interconnection queue. The project entered the queue on November 10, 2022, with a proposed commercial operation date of June 1, 2027.
The interconnection agreement (IA) for PJM-AI2-007 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) for the project is the Rocky Road 138kV substation. The project has appeared in recent news coverage regarding energy storage development in the region.
Generated from interconnection queue and public data sources
State
IL
County
Kane
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Rocky Road 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-007