PJM-AI2-014
37.9 MW generation in Kankakee, IL · In queue since November 2022 · Proposed COD May 2026
37.9 MW
Capacity
1
Components
Solar
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 6m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-05-29
The proposed project PJM-AI2-014 is a 37.9 MW solar generation project located in Kankakee County, Illinois. The project is in the PJM interconnection queue, having entered the queue on November 30, 2022, with a proposed commercial operation date of May 29, 2026. The interconnecting utility is ComEd.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is the Kankakee 138 kV substation.
Generated from interconnection queue and public data sources
State
IL
County
Kankakee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Kankakee 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KANKAKEE138 KV T3
- POI Substation
- AEP Kankakee Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-014