PJM-AI2-015
30 MW storage in Lee, IL · In queue since December 2022 · Proposed COD November 2025
30 MW
Capacity
1
Components
Battery
3y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 11m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-11-30
PJM-AI2-015 is a proposed 30 MW battery storage project located in Lee County, Illinois. The project is interconnected within the PJM Interconnection queue, having entered the queue on December 1, 2022. Its proposed commercial operation date is November 30, 2025. The project's interconnection agreement status is listed as "In Progress (unknown study)".
The proposed project, which will connect to the Nelson-Electric Junction 345 kV point of interconnection, is located within the ComEd service territory. The project consists of 30 MW of battery storage capacity.
Generated from interconnection queue and public data sources
State
IL
County
Lee
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Nelson-Electric Junction 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-015