PJM-AI2-020
19 MW generation in Warren, VA · In queue since December 2022 · Proposed COD December 2022
19 MW
Capacity
1
Components
Gas
3y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Total Duration
<1 month
Schedule
41 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2022-12-31
PJM-AI2-020 is a proposed 19 MW gas-fired generation project located in Warren County, Virginia. The project is in the PJM interconnection queue, having entered on December 10, 2022, with a proposed commercial operation date of December 31, 2022. Dominion is listed as the utility.
The interconnection agreement for the project is currently listed as "In Progress (unknown study)". The point of interconnection is the Warren County 500 kV substation.
Generated from interconnection queue and public data sources
State
VA
County
Warren
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Warren County 500 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- FRONTROY21 KV WARCOCT2
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.