PJM-AI2-030
50 MW hybrid in Adams, OH · In queue since January 2023 · Proposed COD December 2024
50 MW
Capacity
1
Components
Solar
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 11m
Schedule
17 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-20
PJM-AI2-030 is a proposed 50 MW hybrid solar and battery project located in Adams County, Ohio. The project, consisting of 50 MW of solar generation, is interconnected within the PJM Interconnection queue. The queue entry date is January 18, 2023, with a proposed commercial operation date of December 20, 2024. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection (POI) is the Poplar Flat Switch - Brown Hill 69 kV line.
Generated from interconnection queue and public data sources
State
OH
County
Adams
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Poplar Flat Switch - Brown Hill 69 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-030