PJM-AI2-037
142 MW generation in King And Queen, VA · In queue since January 2023 · Proposed COD December 2027
142 MW
Capacity
1
Components
Solar
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-12-31
PJM-AI2-037 is a proposed solar generation project with a total capacity of 142 MW. The project is located in King And Queen County, Virginia, and is being developed within the Dominion service area. It consists of 142 MW of solar photovoltaic generation.
The project is currently active in the PJM interconnection queue, having entered the queue on January 25, 2023. Its proposed commercial operation date is December 31, 2027. The interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Lauraville-Dunbrooke 115kV line.
Generated from interconnection queue and public data sources
State
VA
County
King And Queen
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Lauraville-Dunbrooke 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.