PJM-AI2-039
100 MW storage in Surry, VA · In queue since February 2023 · Proposed COD September 2026
100 MW
Capacity
1
Components
Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
PJM-AI2-039 is a proposed 100 MW battery storage project located in Surry County, Virginia. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 1, 2023, with a proposed commercial operation date of September 30, 2026. Dominion is the utility associated with the project.
The interconnection agreement (IA) status for the project is listed as "In Progress (unknown study)". The point of interconnection (POI) is Poolesville 230kV.
Generated from interconnection queue and public data sources
State
VA
County
Surry
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Poolesville 230kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- POOLSVIL35 KV TX1
- POI Substation
- Poolesville Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-039