PJM-AI2-040
75 MW storage in Orange, VA · In queue since February 2023 · Proposed COD September 2026
75 MW
Capacity
1
Components
Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
PJM-AI2-040 is a proposed 75 MW battery storage project located in Orange County, Virginia. The project is in the PJM interconnection queue as of February 1, 2023, with a proposed commercial operation date of September 30, 2026. Dominion is the utility and the point of interconnection is at Orange 115kV.
The interconnection agreement status is listed as "In Progress (unknown study)". The project consists solely of battery storage, with a total capacity of 75 MW. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
VA
County
Orange
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Orange 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WORANGE 230 KV WORNGESP
- POI Substation
- West Orange Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.