50 MW storage in Louisa, VA · In queue since February 2023 · Proposed COD September 2026
50 MW
Capacity
1
Components
Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 7m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-09-30
PJM-AI2-042 is a proposed 50 MW battery storage project located in Louisa County, Virginia. The project is in the PJM interconnection queue, having entered on February 1, 2023, with a proposed commercial operation date of September 30, 2026. Dominion is the utility associated with the project.
The interconnection agreement for PJM-AI2-042 is currently listed as "In Progress (unknown study)". The point of interconnection is Paytes 115kV. The project is currently listed as active in the interconnection queue.
Generated from interconnection queue and public data sources
State
VA
County
Louisa
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Paytes 115kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PAYTESDP115 KV TX2
- POI Substation
- Paytes Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.