PJM-AI2-056
3.78 MW generation in Erie, PA · In queue since February 2023 · Proposed COD February 2024
3.78 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1 year
Schedule
27 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-02-06
The proposed project PJM-AI2-056 is a 3.78 MW solar generation project located in Erie County, Pennsylvania. It is interconnected within the PJM Interconnection queue, having entered the queue on February 23, 2023. The proposed commercial operation date is February 6, 2024.
The interconnection agreement status is listed as "In Progress (unknown study)". The project is located within the PENELEC utility territory and its point of interconnection is Fairview East 34.5 kV.
Generated from interconnection queue and public data sources
State
PA
County
Erie
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
PENELEC
Entity
PJM
Service Type
—
Point of Interconnection
Fairview East 34.5 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-056