PJM-AI2-064
35.8 MW generation in Blackford, IN · In queue since February 2023 · Proposed COD January 2026
35.8 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
2y 11m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-01-01
PJM-AI2-064 is a proposed solar generation project with a total capacity of 35.8 MW. The project is located in Blackford County, Indiana, within the PJM Interconnection region. The queue entry date is February 23, 2023, with a proposed commercial operation date of January 1, 2026. The interconnection utility is AEP.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The point of interconnection is the Desoto - Keystone 345 kV line. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
Blackford
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Desoto - Keystone 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- KEYSTONE20 KV UNIT 1
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-064