PJM-AI2-065
12.8 MW generation in Dekalb, IN · In queue since February 2023 · Proposed COD June 2026
12.8 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 4m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-06-01
PJM-AI2-065 is a proposed solar generation project with a total capacity of 12.8 MW, located in Dekalb County, Indiana. The project is in the PJM interconnection queue, having entered the queue on February 23, 2023. The proposed commercial operation date is June 1, 2026. The interconnection agreement status is listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection is the Varner - Sours 138 kV line.
Generated from interconnection queue and public data sources
State
IN
County
Dekalb
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Varner - Sours 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-065