PJM-AI2-067
20 MW generation in Lunenburg, VA · In queue since February 2023 · Proposed COD March 2027
20 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-03-01
PJM-AI2-067 is a proposed solar generation project located in Lunenburg County, Virginia. The project, with a total capacity of 20 MW, is being developed within the Dominion service area. It is currently listed as active in the PJM interconnection queue, with an entry date of February 24, 2023, and a proposed commercial operation date of March 1, 2027.
The interconnection agreement (IA) for PJM-AI2-067 is currently listed as "In Progress (unknown study)". The point of interconnection (POI) is the Lunenburg-Nutbush 115 kV line.
Generated from interconnection queue and public data sources
State
VA
County
Lunenburg
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
Dominion
Entity
PJM
Service Type
—
Point of Interconnection
Lunenburg-Nutbush 115 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- DOMINION HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.