PJM-AI2-068
250 MW storage in Monmouth, NJ · In queue since February 2023 · Proposed COD December 2026
250 MW
Capacity
1
Components
Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 10m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-12-31
PJM-AI2-068 is a proposed 250 MW battery storage project located in Monmouth County, New Jersey. The project is interconnected to the Jersey Central Power & Light (JCPL) system via the Larabee - Atlantic 230 kV point of interconnection. It entered the PJM interconnection queue on February 24, 2023, with a proposed commercial operation date of December 31, 2026.
The project's interconnection agreement status is listed as "In Progress (unknown study)". The listed developer is PJM. Recent news coverage of the project is available.
Generated from interconnection queue and public data sources
State
NJ
County
Monmouth
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
JCPL
Entity
PJM
Service Type
—
Point of Interconnection
Larabee - Atlantic 230 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.