PJM-AI2-084
78 MW generation in Morrow, OH · In queue since February 2023 · Proposed COD December 2025
78 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 10m
Schedule
4 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-12-31
PJM-AI2-084 is a proposed solar generation project with a total capacity of 78 MW, located in Morrow County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 27, 2023, with a proposed commercial operation date of December 31, 2025. The interconnecting utility is ATSI.
The interconnection agreement for PJM-AI2-084 is currently listed as "In Progress (unknown study)". The point of interconnection is the Galion 138 kV VI substation.
Generated from interconnection queue and public data sources
State
OH
County
Morrow
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ATSI
Entity
PJM
Service Type
—
Point of Interconnection
Galion 138 kV VI
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- GALION 34.5 KV BLOSSOSP
- POI Substation
- Galion Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.