PJM-AI2-089
71 MW generation in New Castle, DE · In queue since February 2023 · Proposed COD November 2024
71 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Total Duration
1y 9m
Schedule
18 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-11-15
PJM-AI2-089 is a proposed solar generation project with a total capacity of 71 MW, located in New Castle County, Delaware. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 28, 2023. The proposed commercial operation date is November 15, 2024. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)". The interconnecting utility is Delmarva Power & Light (DPL), and the point of interconnection (POI) is the Cedar Creek 138 kV substation.
The development project consists solely of solar generation, with 71 MW of solar photovoltaic (PV) capacity. The project's status is currently listed as active within the PJM queue.
Generated from interconnection queue and public data sources
State
DE
County
New Castle
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
DPL
Entity
PJM
Service Type
—
Point of Interconnection
Cedar Creek 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- WESTERN HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- CEDARCRE34.5 KV CEDARSP
- POI Substation
- Cedar Creek Substation