PJM-AI2-091
22.7 MW generation in Paulding, OH · In queue since March 2023 · Proposed COD February 2023
22.7 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-27
PJM-AI2-091 is a proposed wind generation project with a total capacity of 22.7 MW. The project is located in Paulding County, Ohio, and interconnects to the PJM Interconnection queue. The queue entry date is March 2, 2023, with a proposed commercial operation date of February 27, 2023. The interconnection agreement status is listed as "In Progress (unknown study)". The designated point of interconnection is the Lincoln-Sterling 138kV line, and the interconnecting utility is AEP.
The development project consists solely of wind generation, with all 22.7 MW of capacity attributed to this technology. The project is currently listed as "active" within the PJM queue.
Generated from interconnection queue and public data sources
State
OH
County
Paulding
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Lincoln-Sterling 138kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-091