PJM-AI2-096
54 MW generation in White, IN · In queue since March 2023 · Proposed COD February 2023
54 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-27
PJM-AI2-096 is a proposed 54 MW wind generation project located in White County, Indiana. The project, which entered the PJM interconnection queue on March 1, 2023, consists of 54 MW of wind capacity. The proposed commercial operation date is February 27, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is interconnected to the Olive-Dequine 345kV point of interconnection and is within the service territory of utility AEP. The project is currently listed as active in the PJM queue.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Olive-Dequine 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-096