PJM-AI2-103
106.4 MW generation in Randolph, IN · In queue since February 2023 · Proposed COD February 2023
106.4 MW
Capacity
1
Components
Wind
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
<1 month
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-27
PJM-AI2-103 is a proposed wind generation project with a total capacity of 106.4 MW. The project is located in Randolph County, Indiana, within the PJM Interconnection region. The queue entry date is February 28, 2023, with a proposed commercial operation date of February 27, 2023. The interconnection agreement status is listed as "In Progress (unknown study)".
The project is interconnected to the Desoto-Tanners Creek 345kV point of interconnection and is sponsored by AEP. The project is currently listed as active in the PJM interconnection queue.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Desoto-Tanners Creek 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-103