PJM-AI2-104
100 MW generation in Mclean, IL · In queue since February 2023 · Proposed COD February 2023
100 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
<1 month
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-27
PJM-AI2-104 is a proposed solar generation project with a total capacity of 100 MW, located in McLean County, Illinois. The project is interconnected within the PJM Interconnection queue, with an entry date of February 28, 2023. The proposed commercial operation date is February 27, 2023.
The interconnection agreement (IA) status for PJM-AI2-104 is listed as "In Progress (unknown study)". The point of interconnection (POI) is Blue Mound I, and the utility is ComEd.
Generated from interconnection queue and public data sources
State
IL
County
Mclean
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Blue Mound I
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- 989 TWIN34.5 KV HTRAILWF
- POI Substation
- Blue Mound Substation