PJM-AI2-106
106.4 MW generation in Livingston, IL · In queue since February 2023 · Proposed COD February 2023
106.4 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
<1 month
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-27
PJM-AI2-106 is a proposed solar generation project located in Livingston County, Illinois, within the PJM Interconnection region. The project, with a total capacity of 106.4 MW, consists entirely of solar photovoltaic technology. Its interconnection request was submitted to the PJM queue on February 28, 2023, with a proposed commercial operation date of February 27, 2023. The point of interconnection is the Pontiac MidPoint-Brokaw 345kV line, and the interconnecting utility is ComEd.
The project's interconnection status is currently listed as "In Progress (unknown study)".
Generated from interconnection queue and public data sources
State
IL
County
Livingston
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
ComEd
Entity
PJM
Service Type
—
Point of Interconnection
Pontiac MidPoint-Brokaw 345kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- N ILLINOIS HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-106