PJM-AI2-107
31.7 MW generation in Hardin, OH · In queue since March 2023 · Proposed COD February 2023
31.7 MW
Capacity
1
Components
Wind
3y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
3y 2m
Schedule
39 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-02-27
The proposed project PJM-AI2-107 is a 31.7 MW wind generation project located in Hardin County, Ohio. The project is interconnected within the PJM Interconnection queue, having entered the queue on March 1, 2023. The proposed commercial operation date is February 27, 2023. The interconnection agreement status is currently listed as "In Progress (unknown study)".
The project is being developed within the American Electric Power (AEP) service territory and connects to the Ada-Dunkirk 69kV point of interconnection. The project consists solely of 31.7 MW of wind generation capacity.
Generated from interconnection queue and public data sources
State
OH
County
Hardin
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Ada-Dunkirk 69kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-107