PJM-AI2-110
46 MW generation in Randolph, IN · In queue since February 2023 · Proposed COD October 2023
46 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Total Duration
8 months
Schedule
31 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2023-10-31
PJM-AI2-110 is a proposed solar generation project with a total capacity of 46 MW, located in Randolph County, Indiana. The project is interconnected within the PJM Interconnection queue, having entered the queue on February 28, 2023. The proposed commercial operation date is October 31, 2023.
The interconnection agreement (IA) status for PJM-AI2-110 is listed as "In Progress (unknown study)". The interconnecting utility is AEP, and the point of interconnection (POI) is the Losantville 345 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Losantville 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-110