PJM-AI2-111
84 MW generation in White, IN · In queue since February 2023 · Proposed COD October 2025
84 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Total Duration
2y 8m
Schedule
6 months past proposed COD
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-10-31
PJM-AI2-111 is a proposed solar generation project located in White County, Indiana, within the PJM Interconnection region. The project, with a total capacity of 84 MW, consists entirely of solar photovoltaic technology. The interconnecting utility is AEP.
The project entered the PJM interconnection queue on February 28, 2023, with a proposed commercial operation date of October 31, 2025. Its interconnection agreement status is currently listed as "In Progress (unknown study)". The point of interconnection is Meadow Lake 345 kV.
Generated from interconnection queue and public data sources
State
IN
County
White
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Meadow Lake 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- MEADOWLK34.5 KV MEDWLKWF
- POI Substation
- Meadow Lake Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.