PJM-AI2-112
42 MW generation in Randolph, IN · In queue since February 2023 · Proposed COD October 2026
42 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2026-10-31
PJM-AI2-112 is a proposed solar generation project located in Randolph County, Indiana, within the PJM Interconnection region. The project, with a total capacity of 42 MW, consists entirely of solar photovoltaic generation. The queue entry date for PJM-AI2-112 is February 28, 2023, with a proposed commercial operation date of October 31, 2026. The interconnection agreement (IA) status is currently listed as "In Progress (unknown study)".
The proposed point of interconnection (POI) is the Bluff Point-Randolph 138 kV line. The transmission utility is AEP.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Bluff Point-Randolph 138 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-112