PJM-AI2-120
52.5 MW generation in Randolph, IN · In queue since February 2023 · Proposed COD October 2027
52.5 MW
Capacity
1
Components
Solar
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Total Duration
4y 8m
Interconnection request submitted to ISO/RTO
PJM processes interconnection requests through multi-phase System Impact Studies (SIS).
Typical: ~48 months (historically longest)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-10-31
PJM-AI2-120 is a proposed solar generation project with a total capacity of 52.5 MW. The project is located in Randolph County, Indiana, and is interconnected within the PJM Interconnection region, with AEP as the utility. The project entered the PJM queue on February 28, 2023, and has a proposed commercial operation date of October 31, 2027.
The interconnection agreement (IA) for PJM-AI2-120 is currently in progress, with the specific study phase unknown. The point of interconnection (POI) is the Losantville 345 kV substation.
Generated from interconnection queue and public data sources
State
IN
County
Randolph
Grid Region
PJM Interconnection
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
PJM
Service Type
—
Point of Interconnection
Losantville 345 kV
Data Source
LBNL + Live
- ISO / RTO
- PJM
- Trading Hub
- AEP-DAYTON HUB
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project PJM-AI2-120